Pre-construction
Site review, test fits, BOQ, landlord interfaces, working drawings, procurement schedule and risk identification.
Any contractor can promise “on time”. We publish what we recorded: our Vedant Petrochem fit-out was handed over in about 10 weeks, and a typical Hyderabad office runs 8 to 14 weeks from signed BOQ to occupancy, depending on carpet area and landlord approvals. Workstations, cabins, meeting rooms, MEP coordination and furniture run as one sequenced programme, with a weekly report of hours, blockers and dated photos—so any delay is recorded the week it happens.
Published · Updated · Figures prepared by Gogineni Kalyaan Kumar, Principal, BOQ & estimation


A workplace is not finished when the joinery is installed. It is finished when services, teams, vendors and handover documentation are ready for occupancy.
A Hyderabad office fit-out begins with pre-construction: a site review, test fits, a BOQ, landlord interfaces, working drawings, a procurement schedule and early risk identification, so cost and programme are fixed before any partition goes up. Execution then runs partitions, ceilings, flooring, workstations, cabins, electrical, lighting, HVAC coordination, signage and loose furniture as one sequenced programme rather than trades competing for the same site access. Handover closes the project with testing coordination, finish QC, snag closure, cleaning, warranties and occupation-ready documentation, so the workplace is genuinely ready — not just visually complete — on the day teams are scheduled to move in. This three-stage discipline is what keeps a fit-out tied to an operational date rather than a construction milestone. Running all three stages under one team removes the handoff gaps that typically appear when design, execution and facilities management are contracted separately — the same gaps that usually surface as an unassigned snag list on move-in day.
Site review, test fits, BOQ, landlord interfaces, working drawings, procurement schedule and risk identification.
Partitions, ceilings, flooring, workstations, cabins, electrical, lighting, HVAC coordination, signage and loose furniture.
Testing coordination, finish QC, snag closure, cleaning, warranties and occupation-ready documentation.
Vedant Petrochem’s full office fit-out combined brand-led reception areas with practical workstation, meeting and leadership spaces. Also delivered: KG360, a 5,450 sq ft office in Chennai handed over in about 12 weeks, the Vridhi office in Chennai, and five retail and F&B outlets in Hyderabad, listed on the Hyderabad commercial case studies page.



Two offices with the same carpet area can price very differently depending on these factors.
Two Hyderabad offices with identical carpet area can price very differently, and three factors usually explain the gap. Finish specification — workstation brand, flooring grade and ceiling detailing — moves the budget more than headcount does, since these choices apply per square foot regardless of how many desks fit. Building constraints matter just as much: landlord NOCs, fire and life-safety compliance, and the existing condition of base-building services can add cost and time before finishing work even starts. The target occupancy date is the third lever — a fast-tracked programme needs parallel-running trades and earlier procurement commitments, both of which carry a premium. Typical Hyderabad office fit-outs run 8 to 14 weeks from signed BOQ to occupancy, depending on carpet area and landlord approval timelines. Reviewing these three factors early, before design is finalised, is what keeps a fit-out budget close to its first estimate rather than drifting upward once site work has already started.
Workstation brand, flooring grade and ceiling detailing move budgets more than headcount does.
Landlord NOCs, fire and life-safety compliance, and existing services condition affect both cost and schedule.
Fast-tracked programmes need parallel-running trades and earlier procurement commitments.
Site execution across Hyderabad’s principal business districts, subject to project scope and building access conditions.
AlcorOne publishes its office rate instead of quoting it only on request: ₹3,000–10,000 per sq ft of carpet area, exclusive of GST. The four grades below apply in every city we execute in — Hyderabad differences sit inside the band rather than shifting it, and which grade a floor plate falls into is decided by specification and programme, not by headcount.
| Fit-out grade | Typical specification | Rate (₹/sq ft carpet) | Programme |
|---|---|---|---|
| Lean — startup & back-office | Open-plan led with a handful of cabins, laminate joinery, grid ceiling over most of the plate, catalogue LED lighting, ductable or split air conditioning, entry-grade workstations | ₹3,000–4,200 | 5–9 weeks |
| Standard corporate — most commercial floors | Cabin and open-plan mix, single-glazed partitions, full gypsum and grid ceiling, vinyl or laminate flooring, VRF or ductable HVAC, branded workstations, meeting-room AV provisions | ₹4,200–6,000 | 8–12 weeks |
| Premium — head office & client-facing | Reception in stone and veneer, acoustically treated meeting rooms, double-glazed partitions, specified lighting, VRF with BMS interface, branded ergonomic workstations and task chairs | ₹6,000–8,000 | 12–16 weeks |
| Boardroom grade — experience-led floors | Bespoke joinery and feature ceilings, acoustic pods, integrated AV throughout, imported furniture, full services integration and commissioning | ₹8,000–10,000 | 14–20 weeks |
Basis: AlcorOne execution rates as of , exclusive of GST. Indicative range for planning; the binding figure comes from an itemised BOQ against the actual site measurements and specification.
The band is all-in on the four heads that make up an office fit-out: partitions, ceilings, flooring and joinery; electrical, lighting, fire and data; HVAC; and loose furniture and workstations. Outside it sit GST, landlord deposits and fit-out charges, statutory NOC and fire clearance fees, anything in the landlord's base-building scope, IT active hardware and end-user devices, pantry appliances, and access control, CCTV or BMS integration — those are quoted as named lines rather than assumed inside the rate. This matters when comparing quotes, because a rate that leaves HVAC and furniture out is not a lower price, it is a smaller scope. The full inclusion and exclusion list, the specification ladder that moves a floor from ₹3,000 to ₹10,000, and the per-workstation arithmetic are published on our office fit-out cost page, linked below.
Every rate in the band above pays for the same four heads: builder's work, MEP, HVAC and furniture. Moving up a grade doesn't add heads; it changes what each one carries. This is the breakdown to hold any office quote against, ours included.
| Cost head | What it covers | Lean | Standard corporate | Premium |
|---|---|---|---|---|
| Builder's work | Partitions, glazed fronts, doors, ceilings, flooring, painting, joinery | Painted gypsum partitions, few cabins; mineral fibre grid ceiling; vitrified tile or basic vinyl | Gypsum plus single-glazed fronts; grid plus gypsum in cabins and corridors; vinyl or laminate | Double-glazed acoustic partitions with veneer or stone reveals; feature ceilings; engineered timber, stone at reception |
| MEP | Electrical distribution from the landlord's tap-off, raw and UPS power, lighting and controls, fire modifications, data cabling | Catalogue LED panels | Panels plus linear and downlight zones | Specified fittings, dimming and scene control |
| HVAC | System, ducting, grilles, controls, commissioning and balancing | Split or ductable units | VRF, zoned | VRF with BMS interface, fresh air and CO₂ control |
| Furniture | Workstations, chairs, meeting tables, soft seating, storage | Entry-grade workstations, stack chairs | Branded workstations, ergonomic task chairs | Imported systems furniture, height-adjustable desks |
| Site and handover | Protection, barricading, debris removal, snag closure, as-builts, test reports | Sequential trades | Partial overlap | Compressed, parallel trades and expedited procurement |
Why there are no percentages here yet: we will publish each head's share once we have enough completed office BOQs covering all four heads to give a range, rather than one project's split dressed up as a rule.
One furniture line with a number and no items is a number with nothing specified behind it. Ask for workstations, chairs and tables listed by model.
A quote without HVAC or furniture is not cheaper. It is a smaller scope at a similar-looking rate, so price the missing head before comparing.
If partitions and ceilings carry most of the quote at the same rate per sq ft, something has usually been thinned out of services or furniture to fit the price. Ask which lines shrank.
Where to put the money first: services before finishes, because services are the part that cannot be upgraded during the lease. In order, acoustic separation in meeting rooms, the cabin-to-open-plan ratio, the air-conditioning selection, lighting and controls, then data and AV in every room that will host a call. Workstations, furniture and finishes can be upgraded later; what sits above the ceiling is fixed once it closes. The reasoning behind that order is on our office fit-out cost page, and a blank office BOQ in this format is a free download.
Buyers search for all of these interchangeably — office interior designers, office fit-out contractors, commercial interior contractors, turnkey interior contractors, an office design and build company. They are not the same product, and the difference decides who is accountable when the site does not match the drawing. Here is where we sit, plainly.
AlcorOne is an execution-first commercial fit-out contractor. We deliver turnkey office interiors against an itemised Bill of Quantities you sign before site work starts, with material grade stated per zone. If you are searching for office fit-out contractors in Hyderabad, that is exactly what this is.
We handle design and execution together where you want a single point of accountability, and we build to your architect's or studio's drawings where you already hold a set. What we are not is a design-led studio. Where the central problem is architectural rather than one of delivery, an independent studio is the better first appointment — the full comparison is in our studio versus contractor guide.
Corporate office interiors, workspace design and space planning for Hyderabad floor plates — cabin and open-plan mix, meeting rooms, reception, pantry and the services coordination above the ceiling. Office space planning is part of the fit-out scope here, not a separate fee we bolt on — as an office fit-out company we price the layout work inside the BOQ rather than as a standalone design engagement.
Office renovation on a second-generation space means stripping a previous tenant's fit-out before anything new begins, which is its own line and routinely underestimated. We also phase work zone by zone around a working team — see the timeline page for what occupied working does to a programme.
The same team delivers retail fit-outs, restaurant and cafe interiors, showrooms, mall kiosks and hospitality fit-outs in Hyderabad, with five delivered retail and F&B outlets in this city.
Turnkey means one contract and one number — it does not mean everything. Which lines are inside a commercial fit-out quote and which are your landlord's is set out in full on our turnkey scope page, including the eight exclusions that most often go unstated.
Considering a project management consultant above the contractor? Here is when a PMC earns its fee, and when an open BOQ already gives you what it sells — including the projects where we would tell you to appoint one.
Pre-construction site review and BOQ, execution of partitions, ceilings, workstations, cabins, electrical and HVAC coordination, and a full occupancy-ready handover documentation package.
Typical Hyderabad office fit-outs run 8–14 weeks from signed BOQ to occupancy, depending on carpet area and landlord approval timelines.
Yes. The Vedant Petrochem office in Hyderabad was a full fit-out — marble reception, linear LED ceiling, glass cabins, open workstations, meeting rooms and an MD cabin — handed over in about 10 weeks. In Chennai, the 5,450 sq ft KG360 office took about 12 weeks. The same team has delivered five retail and F&B outlets in Hyderabad.
Finish specification, building constraints such as landlord NOCs and fire compliance, and the target occupancy date move cost more than headcount does.
Financial District, HITEC City, Gachibowli, Madhapur, Kondapur, Jubilee Hills and Banjara Hills, subject to project scope.
Yes — phased fit-outs are sequenced by zone with noisy or disruptive work scheduled outside working hours where the landlord and existing tenants require it.
Yes — NOC approvals, utility shutdowns, loading-dock access and building fit-out rules are tracked directly with the landlord or facility manager alongside the site programme.
Both. We handle design and execution together where you want a single point of accountability, and we build to your architect’s or studio’s drawings where you already hold a set, pricing them into an itemised BOQ before site work starts. Where the central problem is architectural rather than delivery, we will say an independent studio is the better first appointment — see the studio versus contractor guide.
₹3,000–10,000 per sq ft of carpet area, exclusive of GST — all-in, including electrical, lighting, fire and data, HVAC, and loose furniture and workstations. A lean open-plan floor lands at ₹3,000–4,200, a standard corporate floor at ₹4,200–6,000, a premium head office at ₹6,000–8,000, and boardroom-grade work at ₹8,000–10,000. The same band applies in every city we execute in; the binding figure comes from an itemised BOQ measured against your actual carpet area.
Include the carpet area, target occupancy date, landlord status, whether the space is currently occupied, and whether a design package already exists.