Have you delivered a mall unit in Chennai?
Yes — a food-court kiosk for Madurai Famous Jigarthanda in a Chennai mall. Beyond that, our delivered Chennai retail work is a high-street F&B fit-out (Dessert Addictions), and our commercial record here also includes two completed offices. If a delivered Chennai in-line mall unit specifically is a shortlisting requirement, we do not yet meet that narrower bar — the Jigarthanda kiosk is a food-court unit, not a large in-line store.
How long does a mall unit fit-out take in Chennai?
Reckon on four to eight weeks of site work for a typical unit — then add the approval cycle in front of it, which is the part most programmes underestimate. Drawing approval and its comments commonly run two to four weeks, and because work is night-only, each calendar day yields roughly half a day of output. We lodge the submission the day the unit is confirmed, since that is the only time in the programme that is genuinely recoverable.
What is a fit-out manual and why does it matter so much?
It is the centre's rulebook for tenant work, and it is a design input rather than a compliance checklist. It fixes the shopfront line and signage zone, the permitted materials, ceiling void and sprinkler coordination, flooring transitions, the barricade specification, working hours and the approval format itself. Because it governs the design, it has to be read before drawings are produced — a set that ignores it is refused at approval, and that refusal is paid for in weeks of a fit-out window you are already renting.
Do you handle the mall approvals and drawings?
Yes. We produce the approval set in the centre's own format, submit it, and run the comment cycle through to sign-off, together with contractor gate passes and worker documentation. What we cannot do is make the decision — that is the mall's. What we can control is how complete the submission is, and completeness is what decides whether it clears in one cycle or three.
Why do malls restrict work to night hours?
Because tenant work cannot disturb trading tenants or shoppers. In practice that means a booked service-lift slot, materials moved only after closing, and a productive window of roughly six to eight hours instead of a full working day. It does not make the fit-out harder to do — it makes the programme longer, and the programme has to be built that way from the start rather than compressed later.
How is a kiosk or RMU different from a mall unit?
It is mostly a factory-build problem. The unit is fabricated off site, delivered, and assembled in a very short overnight window on a trading concourse, so dimensional precision carries the risk — there is no chance to trim something to fit once it is on the floor. Footprint, the centre's height restriction and the power tie-in point are all confirmed before fabrication starts, not at delivery.