# In a mall, the programme is set by someone else.

Mall fit-outs run on the mall's terms: an approval drawing set, a fit-out manual, a barricade specification, night-only working, and a handover date after which your lease charges rent whether you are trading or not. AlcorOne works that process as carefully as the joinery.

## The mall process, *handled properly.*

Most delay on a mall unit is administrative, not physical. An approval returned with comments, a contractor without a mall gate pass, or a barricade that fails inspection each cost days you are already paying rent for.

### Fit-out manual compliance

Every mall issues one, and it governs shopfront line, signage zone, ceiling void access, sprinkler and smoke-detector coordination, flooring transitions and permitted materials. We read it before designing, not after an approval is rejected.

### Approval drawings

Malls approve a defined drawing set before mobilisation. We prepare and submit it, and handle the comment cycle. This is where weeks are typically lost, so it starts the day the unit is confirmed.

### Barricade and hoarding

Built to the mall's specification, with approved graphics, before any work begins. A non-compliant barricade gets the site shut down on the first inspection.

### Night-only working

Most malls permit fit-out work only after trading hours, with materials moved through a service route on a booked slot. The programme is built around that from the start rather than discovering it in week one.

### Services coordination overhead

Sprinkler drops, smoke detectors, and the mall's HVAC and electrical tie-ins are all inspected. Every one is a dependency on a mall engineer's availability, not just on our labour.

### Kiosks and RMUs

Kiosks are largely factory-built, delivered and assembled inside a very short window. Precision matters more than on a fixed unit — a kiosk that does not fit its footprint cannot be adjusted on site in a trading mall.

## Retail joinery *from completed work.*

### Display units

Modular · Integrated lighting

### Counters and cash wrap

Sealed edges · Cable management

### Shopfront line

Signage zone · Glazing · Lighting

## Why the lease date *drives everything.*

A mall fit-out has a financial clock on it that a high-street unit does not.

### Rent starts regardless

Most mall leases begin charging from a fixed date whether the unit is trading or not. Every week of fit-out overrun is rent paid on a closed shop, which is why the approval cycle deserves as much attention as the build.

### Fixed fit-out window

Malls grant a defined fit-out period, sometimes with penalties for overrun. Long-lead items — custom glazing, imported signage, specific flooring — are ordered before the window opens, not inside it.

### Handover inspection

The mall inspects before permitting trading. Sprinkler coordination, signage compliance, flooring transitions and barricade removal are all checked. We schedule so nothing outstanding sits between us and that inspection.

## Vizag mall and *high-street corridors.*

Dwaraka NagarJagadambaAsilmettaMVP ColonySiripuramGajuwakaBeach RoadMadhurawada

## Sources & *references.*

Standards, regulatory registries, and manufacturer references that back the material grades, pricing framework, and compliance points in this guide:

- [Andhra Pradesh RERA — project registry](https://rera.ap.gov.in/)

## Questions we *hear most.*

### How long does a mall unit fit-out take in Vizag?

Four to eight weeks of site work for a typical unit, but the honest answer includes the approval cycle before it. Mall drawing approval and the comment cycle commonly add two to four weeks, and night-only working roughly halves the productive hours in a day. We start the approval submission the day the unit is confirmed, because that is where the recoverable time is.

### What is a fit-out manual and why does it matter so much?

It is the mall's rulebook for tenant works: shopfront line and signage zone, permitted materials, ceiling void and sprinkler coordination, flooring transitions, barricade specification, working hours, and the service route for materials. It governs the design, so it has to be read before drawings are produced. A design that ignores it will be rejected at approval, and that rejection costs weeks of a fit-out window you are paying rent against.

### Do you handle the mall approvals and drawings?

Yes. We prepare the approval drawing set to the mall's format, submit it, and manage the comment cycle through to sign-off, along with contractor gate passes and worker documentation. The mall's approval decision is theirs, but the completeness and quality of the submission is what determines how many cycles it takes.

### Why do malls restrict work to night hours?

Because tenant fit-out work cannot disturb trading tenants or shoppers. In practice this means a booked service-lift slot, materials moved after closing, and a productive window of roughly six to eight hours instead of a full day. It does not make a fit-out impossible — it makes the programme longer, and it has to be planned that way from the start rather than absorbed as a surprise.

### How is a kiosk or RMU different from a mall unit?

It is mostly a factory-build problem. A kiosk is fabricated off site, delivered, and assembled in a very short overnight window in a trading mall, so dimensional precision matters far more — there is no opportunity to trim something to fit on the concourse. Power tie-in point, footprint dimensions and the mall's height restriction have to be confirmed before fabrication starts, not at delivery.

### What does a mall or kiosk fit-out cost in Vizag?

Kiosks and RMUs are quoted as a fabricated unit plus installation. Mall units are priced from a line-item BOQ after the fit-out manual and unit drawings are reviewed, because the manual itself drives cost — mandated materials, ceiling access requirements and signage specifications are not optional. We separate the approval and compliance scope from the build scope so you can see what the mall's own requirements are adding.

---